Designing fatigue-proof subsea cables

03. ROV

Challenge

Ocean Power Technology (OPT) set out to pioneer grid-scale wave power with “Power Buoys.” The cable had to last 25–30 years offshore. Over 100 million wave cycles, while carrying three-phase power and fiber-optic data and surviving continuous motion at the buoy/termination interface. Conventional designs weren’t built for that lifetime or motion profile. And while the tech needed to be field-proven, the economics for very large farms weren’t there yet. So the system also had to be practical for off-grid deployments where grid connection doesn’t exist.

Solution

DeRegt partnered with OPT from day one so the cable wasn’t an add-on but a core part of the buoy system. Electrically, the umbilical delivered three-phase power at 3.3 kV plus fiber-optic data. Mechanically, fragile fibers were placed near the neutral axis for maximum bend resilience. At the buoy interface, DeRegt engineered a custom bend-stiffener and a smart floating support: buoyancy pressed the stiffener against the structure, removing the need for diver-installed fastenings and reducing local bend strain.

Fatigue was the make-or-break. Instead of waiting decades, DeRegt combined S-N (stress–life) modeling, built from steel-wire fatigue data. With accelerated testing at elevated loads to predict life at operational loads. A dedicated “rotating float fatigue” setup then validated how the cable behaves under continuous wave-induced motion. Together, these methods qualified a design horizon on the order of 100 million cycles.

Deployment needed to be as robust as the design. Cables were pre-terminated, pressure-sealed, and fitted with cam-lock style quick couplings to avoid risky offshore assembly and speed installation. The result was a plug-and-play cable system that blended proven standard components (for reliability and serviceability) with custom protective and dynamic features tuned to the buoy’s motion.

This co-creation approach (electrical + mechanical + termination), validated by analysis and targeted tests, produced a cable system that could genuinely survive the ocean, not just the lab.

Result

The project and the product were a success. OPT’s system was deployed (e.g., Spain and Hawaii), and the custom cables passed extensive lab and at-sea qualification. Demonstrating durability consistent with multi-decade operation. While the economics for very large grid-scale farms weren’t yet viable at the time (hence no mega-arrays), the technology proved itself and has since been used where it makes immediate sense: remote, off-grid locations such as islands or offshore assets that need dependable power without a grid connection.

Importantly, the core idea of large farms has recently regained momentum and is once again considered a credible option for the energy transition. That renewed attention builds on the technical groundwork from projects like this: validated dynamic design, fatigue-proof terminations, and installation practices that turn wave power from concept into deployable infrastructure.

Expert view

“The ocean doesn’t forgive fatigue. That’s why we design beyond it.”

Connect with our ROV specialist

Discover how DeRegt's custom cable solutions can meet your unique requirements. Whether you need cables for short or long distances, our experts are here to help you every step of the way.
  • Feasability check
  • Ask a question
  • Challenge us
Jeroen Romijn

Jeroen Romijn

ROV Cable specialist

Call 06 12 34 56 78

image 6 (1) image 6 (1)

Client success stories

image 6 (1) ROV

Dit is de titel van de case

Placeholder-1 ROV

Dit is de titel van de case

09. Defense-1 ROV

Dit is de titel van de case